Shieldhall Strategic Solution

Construction Site Outdoor With Crane People Working Top View | BRE Group

CEEQUAL Excellent (90.3%) – Client & Design Award
Version 5, Dec 2014 | Glasgow, Scotland

Sustainability Strategy Rating: Excellent (93.0%)

ClientScottish Water
DesignerCH2M with  MWH (sub-consultant)
Assessor: Susan McIvor

Project Summary

Scottish Water determined, through the Glasgow Strategic Studies (GSS) Value Management process, that a new tunnelled sewer to relieve the existing South Side No.1 Sewer in Glasgow is the preferred strategic hydraulic solution to deliver regulatory drivers for the Shieldhall catchment. The new sewerage tunnel is to be constructed from Queens Drive through Queens Park, Pollok Park and Bellahouston Park, connecting into the existing network at Craigton Industrial estate adjacent to the Ayr to Paisley railway line.

The aim of this diversion is to reduce surcharging and backing up of sewerage within the existing system, addressing flooding and Water Quality (WQ) needs identified at Kinning Park Pumping Station, St. Andrews Road CSO, Aikenhead, Burnfield and other key locations.

The Strategic Solution requires construction works to be undertaken in several areas.

The Strategic Tunnel will comprise of a 5.46km long gravity sewer, with a nominal internal diameter of 4650mm. A total of 5No. 15,000 mm internal diameter shafts will be incorporated along the route. The 5No. shafts form part of the permanent works and act as part of the storage of the system, which is approximately 90,000 cubic metres. The tunnel has been sized to convey the Dry Weather Flow (DWF) and provide an increased Peak Flow Factor (PFF) during storm conditions. The tunnel will also provide a significant amount of online storage. No head room has been included in the design of the tunnel.

The new sewer relieves the existing sewerage network and provides the necessary flow conveyance and storm storage. The upstream connection point of the proposed tunnel to the existing network is at Queens Drive, adjacent to Queens Park. From this point, the tunnel shall run to the west side of Glasgow, tying into the network again at Barfillan Drive, Craigton Industrial Estate.

The scheme was assessed using CEEQUAL to Client & Design Award. The construction of the scheme is also being assessed using CEEQUAL. On 7 October 2015 the Excellent Client & Design Award was presented to project team members. A photograph from the presentation is included below.

Shieldhall Strategic Solution | CEEQUAL

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

light rail sustainable and safer city Bybanen Bergen | BRE Group

Bybanen D11 Sentrum

To achieve a more sustainable and safer city, Bybanen Bergen, are building a light rail. The first phase of the ...
Read More
Lillestrøm pumping station | BRE Group

Pumpestasjon PA240 – Lillestrøm Kommune

Construction of a new pumping station infrastructure in the municipality of Lillestrøm. The project has great social significance in terms ...
Read More
Westside Metro Extension Phase One | BRE Group

Birmingham Westside Metro – Centenary Square Extension

The Midland Metro Alliance (MMA) is working on behalf of Transport for West Midlands (TfWM), which is part of the ...
Read More
Musaimeer Pump Station and Outfall Qatar | BRE Group

Musaimeer Pumping Station and Outfall Tunnel

Musaimeer Pump Station and Outfall (MPSO) is one of the unique infrastructure projects of Ashghal which aims to provide a ...
Read More
Bybanen D12 Store Lungegårdsvann | BRE Group

Bybanen D12 Fløen – Kronstad

The Bybanen tram-project is part of the Miljøløftet, a common term for the urban growth agreement and the city infrastructure ...
Read More
DCIM100MEDIADJI 0115JPG | BRE Group

A6 Randalstown to Castledawson Dualling

Delivered by the Department for Infrastructure the A6 Dualling Scheme upgrades 14.7 kilometres of Transport Corridor between Randalstown and Castledawson, ...
Read More

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags