Shieldhall Strategic Solution

CEEQUAL Excellent (90.3%) – Client & Design Award
Version 5, Dec 2014 | Glasgow, Scotland

Sustainability Strategy Rating: Excellent (93.0%)

ClientScottish Water
DesignerCH2M with  MWH (sub-consultant)
Assessor: Susan McIvor

Project Summary

Scottish Water determined, through the Glasgow Strategic Studies (GSS) Value Management process, that a new tunnelled sewer to relieve the existing South Side No.1 Sewer in Glasgow is the preferred strategic hydraulic solution to deliver regulatory drivers for the Shieldhall catchment. The new sewerage tunnel is to be constructed from Queens Drive through Queens Park, Pollok Park and Bellahouston Park, connecting into the existing network at Craigton Industrial estate adjacent to the Ayr to Paisley railway line.

The aim of this diversion is to reduce surcharging and backing up of sewerage within the existing system, addressing flooding and Water Quality (WQ) needs identified at Kinning Park Pumping Station, St. Andrews Road CSO, Aikenhead, Burnfield and other key locations.

The Strategic Solution requires construction works to be undertaken in several areas.

The Strategic Tunnel will comprise of a 5.46km long gravity sewer, with a nominal internal diameter of 4650mm. A total of 5No. 15,000 mm internal diameter shafts will be incorporated along the route. The 5No. shafts form part of the permanent works and act as part of the storage of the system, which is approximately 90,000 cubic metres. The tunnel has been sized to convey the Dry Weather Flow (DWF) and provide an increased Peak Flow Factor (PFF) during storm conditions. The tunnel will also provide a significant amount of online storage. No head room has been included in the design of the tunnel.

The new sewer relieves the existing sewerage network and provides the necessary flow conveyance and storm storage. The upstream connection point of the proposed tunnel to the existing network is at Queens Drive, adjacent to Queens Park. From this point, the tunnel shall run to the west side of Glasgow, tying into the network again at Barfillan Drive, Craigton Industrial Estate.

The scheme was assessed using CEEQUAL to Client & Design Award. The construction of the scheme is also being assessed using CEEQUAL. On 7 October 2015 the Excellent Client & Design Award was presented to project team members. A photograph from the presentation is included below.

Shieldhall Strategic Solution | CEEQUAL

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

E18 Rugtvedt Dørdal | CEEQUAL

E18 Rugtvedt – Dørdal

The project is a 16.5km four-lane motorway in Telemark, Norway with a 110 km/hour speed limit. The state-owned company, Nye ...
Read More
Lahti Southern Ring Road (Vt12), VALTARI alliance

Lahti Southern Ring Road (Vt12), VALTARI alliance

This project, undertaken by the VALTARI alliance, involves the construction of a 4.5km southern ring road, bypassing the center of ...
Read More
RAF Lossiemouth | CEEQUAL

RAF Lossiemouth – AOS Project

The project is a full refurbishment of all major airside pavement surfaces at RAF Lossiemouth for a new Boeing P8 ...
Read More
Stockholm Extended Metro Arenastaden Plattform | CEEQUAL
| CEEQUAL Case Studies, Rail, Scandinavia

Stockholm Extended Metro – Arenastaden

The extension of the Stockholm Metro is vital to make Stockholm a vibrant and accessible city with a sustainable public ...
Read More
Old Colwyn Coastal Defence and Active Travel Scheme | CEEQUAL

Old Colwyn Coastal Defence and Active Travel Scheme

The scheme represented an opportunity to build on the success of previous phases of the Colwyn Bay Waterfront Project with ...
Read More

Get in touch

Contact us now or call us on 0333 014 7880 if you would like to talk to our team about how CEEQUAL can support you.

Tags