Shieldhall Strategic Solution

CEEQUAL Excellent (90.3%) – Client & Design Award
Version 5, Dec 2014 | Glasgow, Scotland

Sustainability Strategy Rating: Excellent (93.0%)

ClientScottish Water
DesignerCH2M with  MWH (sub-consultant)
Assessor: Susan McIvor

Project Summary

Scottish Water determined, through the Glasgow Strategic Studies (GSS) Value Management process, that a new tunnelled sewer to relieve the existing South Side No.1 Sewer in Glasgow is the preferred strategic hydraulic solution to deliver regulatory drivers for the Shieldhall catchment. The new sewerage tunnel is to be constructed from Queens Drive through Queens Park, Pollok Park and Bellahouston Park, connecting into the existing network at Craigton Industrial estate adjacent to the Ayr to Paisley railway line.

The aim of this diversion is to reduce surcharging and backing up of sewerage within the existing system, addressing flooding and Water Quality (WQ) needs identified at Kinning Park Pumping Station, St. Andrews Road CSO, Aikenhead, Burnfield and other key locations.

The Strategic Solution requires construction works to be undertaken in several areas.

The Strategic Tunnel will comprise of a 5.46km long gravity sewer, with a nominal internal diameter of 4650mm. A total of 5No. 15,000 mm internal diameter shafts will be incorporated along the route. The 5No. shafts form part of the permanent works and act as part of the storage of the system, which is approximately 90,000 cubic metres. The tunnel has been sized to convey the Dry Weather Flow (DWF) and provide an increased Peak Flow Factor (PFF) during storm conditions. The tunnel will also provide a significant amount of online storage. No head room has been included in the design of the tunnel.

The new sewer relieves the existing sewerage network and provides the necessary flow conveyance and storm storage. The upstream connection point of the proposed tunnel to the existing network is at Queens Drive, adjacent to Queens Park. From this point, the tunnel shall run to the west side of Glasgow, tying into the network again at Barfillan Drive, Craigton Industrial Estate.

The scheme was assessed using CEEQUAL to Client & Design Award. The construction of the scheme is also being assessed using CEEQUAL. On 7 October 2015 the Excellent Client & Design Award was presented to project team members. A photograph from the presentation is included below.

Shieldhall Strategic Solution | CEEQUAL

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

Ramsdal bridge BREEAM Infrastructure

E39 Mandal øst – Mandal

E39 Mandal East- Mandal city consist of a 7 km long four lane highway that together with the new E39 ...
BREEAM Infrastructure Bybanen D18 Sykkelvei Kronstadtunnelen

Bybanen D18 Sykkelvei Kronstadtunnelen

Project D18 Sykkelvei Kronstadtunnelen is part of the Bybanen-light rail construction stage 4 development scheme. This is the largest development ...
Sustainable Rail construction Leeds Station

Transpennine Route Upgrade (TRU) Leeds Station Capacity

Leeds Station Capacity is the first project to be completed as part of the TRU programme. All TRU projects are ...
BREEAM-Infrastructure-sustainable-Bergen-Norway-underground-station-platforms

Bybanen D13 Haukeland Holdeplass

Bybanen D13 Haukeland Holdeplass is the very first underground station at the light rail system in Bergen, Norway.  It has ...
A77 Maybole bypass southern roundabout sustainable infrastructure

A77 Maybole Bypass Construction Award

The A77 Maybole Bypass reduces journey times on the A77 by diverting traffic away from the High Street of the ...
Drone Photo of new jetty at Thanckes Oil Fuel Depot

Thanckes Oil Fuel Depot Loading Facility & Tank Farm Fire Fighting Upgrade

VolkerStevin constructs a new jetty at Thanckes Oil Fuel Depot to provide fuelling facilities for the Royal Navy at Devonport ...

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags