Reading Sewage Treatment Plant

Reading 1 BRE Group

CEEQUAL Excellent (79.5%) – Whole Team Award
Version 2, Aug 2003 | Reading, England

ClientThames Water
DesignersFaber Mausell (now AECOM)
ConstructionBlack & Veatch and Taylor Woodrow Construction
Assessor: Bill Wood

Project Summary

Design and construction of the new Reading sewage treatment works is being undertaken by an Alliance consisting of the client Thames Water Utilities Limited, Taylor Woodrow and Black & Veatch. The main drivers for the £80m project are to meet new regulated standards for effluent discharge and sludge disposal in addition to eliminating odour nuisance.

The foundations for the project’s CEEQUAL success lay in Thames Water’s determination to set very high standards of environmental performance as one of the initial project objectives – a fact illustrated by the contractual emphasis on environmental management and the presence in the project team of a dedicated Environmental Manager. A thorough Environmental Impact Assessment, completed prior to commencement, contained extensive mitigation measures for the construction phase and enhancement proposals as part of the scheme design – important environmental aspects of civil engineering which are highlighted by the CEEQUAL process. Examples of the former are the air quality and landscape strategies agreed with Reading Borough Council whilst enhancements include creation of mounding as invertebrate sub-strate and the planting of over 20,000 native trees.

The Alliance made an early decision to operate an Environmental Management System (EMS) with the aim of gaining certification to ISO14001. Having achieved certification it is no surprise that the ‘Project Environmental Management’ section of CEEQUAL was one of the project’s highest scoring elements.

Although a somewhat detailed design was required for Planning purposes, thus constraining total design freedom, the scheduling and tracking of decisions on all environmental design matters once on site ensured that nothing ‘slipped through the net’ in the course of making the many decisions that a project of this complexity requires. The ‘Environmental Design Checklist’ is reviewed every two months and all decisions and changes signed off once implications and agreements are reached. This process, and the results from it, is a further contributory factor to the high scoring in the CEEQUAL assessment.

From the early days of extensive site remediation, when an unexpected colony of water voles was successfully relocated under a licence from English Nature, to site controls as part of the EMS, the project to date has a very good environmental record.

Gallery

Reading Sewage Treatment Plant | CEEQUAL

 

Reading Sewage Treatment Plant | CEEQUAL

Reading Sewage Treatment Plant | CEEQUAL

 

Reading Sewage Treatment Plant | CEEQUAL

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

Sea filling winter conditions BREEAM Infrastructure BRE Group

E16 Kvamskleiva

E16 Kvamskleiva was mainly a rock slide protection project in an area with steep mountain sides and frequent ice and ...
Read More
Flomsikring Mjøndalen sentrum Vassenga03 BRE Group

Flomsikring Mjøndalen sentrum – Vassenga

Flomsikring Mjøndalen - Vassenga is part of the flood defence project in Mjøndalen, aiming to reduce the flood risk in ...
Read More
Norway Audnadalen Artist Wichada Treepoonpon Sweco Norge BRE Group

E39 Mandal – Lyngdal øst

Nye Veier AS have, in collaboration with Sweco Norge AS, planned a new four-lane motorway from Mandal River through Lindesnes ...
Read More
Worcestershire Sustainable Infrastructure BRE Group

Worcestershire Parkway Regional Interchange

Worcestershire Parkway is a new station at the intersection of the Worcester to London (OWW line) and Birmingham to Bristol ...
Read More
BREEAM Infrastructure Version 6 for Projects Construction E16 Eggemoen Olum E02 Åsbygda Olum BRE Group

E16 Eggemoen-Olum, E02 Åsbygda-Olum

Skanska won a  contract from the Norwegian public Roads Administration in 2019 to build 10.4 km of new E16 road ...
Read More
Sege Park Sustainable Infrastructure BRE Group

Urban development project Sege Park

Sege Park urban development project is an urban development and regeneration project in Malmö. A former hospital area is being transformed ...
Read More

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags