Paddington Bakerloo Line Link

The complex £40 million Bakerloo Line Link project provides a new 170m pedestrian tunnel link between the Paddington Crossrail Station and London Underground Bakerloo Line platforms.

CEEQUAL Excellent (93.3%) – Whole Team Award + Interim
Version 5, October 2017 | London, England, UK

Sustainability Strategy Rating: Excellent (96.2%)

Client: London Underground Ltd
Designer: Arcadis
Principal Contractor: Costain / Skanska Joint Venture (CSJV)

Assessors: Conor McCone & Polly Gourlay (CSJV)

.

Project summary

The project will ease congestion on the existing London Underground infrastructure and minimise the journey time between Crossrail and the Bakerloo Line. All the works, including new lift access for people with restricted mobility and a new shaft for two new escalators, were completed by Costain Skanska Joint Venture (CSJV).

Gallery

Key achievements

  • Work completely internalised in existing Royal Mail Group building – reducing impact on local heritage, communities, and transport.
  • Reduction in carbon emissions by minimizing lorry movements and transporting spoil by rail.
  • No environmental complaints throughout the project.

Challenges and Achievements

The site is surrounded by sensitive receptors – including hospital buildings and hotels – so the project team aimed to reach the highest environmental and sustainability standards possible.

Historic environment

The Bakerloo Line Link project was awarded to CSJV due to an innovative design that completely internalised the work site within an existing Royal Mail Group building at Paddington. Internalising the site and removing the need for two external shafts has made it possible to avoid impacts on the surrounding local heritage. Surveys were completed to assess the areas and landmarks of key significance and all consents were set out with local stakeholders and Westminster City Council to protect and maintain the historic environment.

Community and Stakeholder Engagement

Internalising the work site within the Royal Mail building also lead to a significant reduction in the project’s impact on the local community and environment. Internalising the works meant all construction, waste removal, deliveries, and loading of excavated tunnel material could be contained within the enclosed site. This reduced the impact on traffic congestion, air quality, noise, vibration and other nuisance related activities. CSJV maintained a good relationship with Westminster City Council throughout the project with regular monthly meetings and clear communication of any potential risks or upcoming work-related nuisance. As a result, the project had no environmental complaints – something which is almost unheard of in such a sensitive environment.

Project Management

CSJV tunnelling team in Paddington Bakerloo Line Underground station

Through utilising the CEEQUAL process the Bakerloo Line Link project was able to achieve enhanced sustainability and performance throughout the design, pre-construction, and construction stages. Steered by the senior management’s weekly HSE inspections, a full time CSJV environmental advisor, and a part-time London Underground environmental manager, have worked through each stage of the project to successfully integrate and deliver positive environmental management in the daily site operations. This has resulted in the beyond expectation CEEQUAL Excellent score of 93.3%.

How did CEEQUAL influence your project?

Including CEEQUAL in the Works Information led to buy in from senior management and early involvement in its implementation. Incorporating the new Project Strategy section of CEEQUAL allowed for early collaboration between the project team and design team in the crucial pre-construction stages of the project. The greatest amount of influence can be identified in these stages and CEEQUAL supported the dialogue between design, client, and construction teams. This in turn led to early design meetings that helped reduce material by minimising the required tunnel profile and promote the adoption of innovative solutions like internalising the work site.

Award presentation

The team received their CEEQUAL certificates at an internal presentation on Friday 9 February 2018.

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

E18 Rugtvedt Dørdal | CEEQUAL

E18 Rugtvedt – Dørdal

The project is a 16.5km four-lane motorway in Telemark, Norway with a 110 km/hour speed limit. The state-owned company, Nye ...
Read More
Lahti Southern Ring Road (Vt12), VALTARI alliance

Lahti Southern Ring Road (Vt12), VALTARI alliance

This project, undertaken by the VALTARI alliance, involves the construction of a 4.5km southern ring road, bypassing the center of ...
Read More
RAF Lossiemouth | CEEQUAL

RAF Lossiemouth – AOS Project

The project is a full refurbishment of all major airside pavement surfaces at RAF Lossiemouth for a new Boeing P8 ...
Read More
Stockholm Extended Metro Arenastaden Plattform | CEEQUAL
| CEEQUAL Case Studies, Rail, Scandinavia

Stockholm Extended Metro – Arenastaden

The extension of the Stockholm Metro is vital to make Stockholm a vibrant and accessible city with a sustainable public ...
Read More
Old Colwyn Coastal Defence and Active Travel Scheme | CEEQUAL

Old Colwyn Coastal Defence and Active Travel Scheme

The scheme represented an opportunity to build on the success of previous phases of the Colwyn Bay Waterfront Project with ...
Read More

Get in touch

Contact us now or call us on 0333 014 7880 if you would like to talk to our team about how CEEQUAL can support you.

Tags