Olympic Park: Media Hub Multi-Storey Car Park (MSCP)

Olympic Park: Media Hub Multi-Storey Car Park | CEEQUAL

CEEQUAL Excellent (93.3%) – Whole Project Award
Version 4, May 2011 | London, England

ClientOlympic Delivery Authority
DesignWalsh Associates and Bryne Brothers Ltd (D&B contractor)
ConstructionCarillion UK Construction (Principal Contractor) with Byrne Brothers Ltd (D&B subcontractor)
Assessor: Chris Gee

Project Summary

The Media Hub provides a range of facilities for the Olympic Park including four buildings; the International Broadcasting Centre; the Main Press Centre; catering village; and multi-storey car park and associated facilities which form the vehicular entry portal to him Park from the A12 at the North West corner of the Park. Vehicles enter via a slip road from the A12 and entry queuing lanes.

During the Olympic Games, the MSCP will act as entry control for international press with in-built ID check and security screening on the 1st floor, with a link bridge to the IBC building. The ground level is designed for coaches with safe drop off zones and coach parking. Upper floors are designated for cars with accessible parking adjacent to the entry suite.

In Legacy mode, it is planned to modify the structure, removing the western half of the car park, fitting permanent cladding and a large array of photovoltaic panels at roof level. This is in accordance with the Olympic Legacy strategy for renewable energy. The main structure has been designed from prefabricated components to ease dis-assembly. The footprint of the western half will be designated for community orientated use after the Games.

The design and construction process responded to the high standards for sustainability set out by the Olympic Delivery Authority, achieving an Excellent Rating under CEEQUAL Version 4 and with a ratified score of 93.3%.

Olympic Park: Media Hub Multi-Storey Car Park | CEEQUAL

Olympic Park: Media Hub Multi-Storey Car Park | CEEQUAL

Challenges

The site allocated for the media Hub and car park within the Olympic Master Plan suffered from ground contamination and presence of ground gases, common with other areas of the Park. Extensive ground remediation works were carried out across the Park with a “soil hospital” where contaminated subsoil and topsoil were collected, treated and recycled. A gas membrane and subsoil contamination monitoring points had to be incorporated.

In common with all Olympic projects, the ODA set exacting standards for sustainability for the design, construction and operational stages. There was a strict monitoring and reporting regime of key performance indicators throughout the construction phase.

Design Development

The structure had to be designed to meet both Games and legacy requirements which are substantially different. Initial designs were developed by Walsh Associates on the site for the portal designated by ODA as part of the Park strategy. Following outline planning clearance for the concept, Byrne Brothers Ltd (specialist concrete structure contractors) were appointed under a Design and Build Contract. Considerable savings in materials and embedded carbon were achieved by the prefabricated design. The design also needed to address the client requirement to demolish 50% of the structure in Legacy mode.

Olympic Park: Media Hub Multi-Storey Car Park | CEEQUAL

Olympic Park: Media Hub Multi-Storey Car Park | CEEQUAL

Sustainability

The robust ODA park-wide sustainability targets were enforced through contract requirements with regular reporting and audits.

The site was adjacent to local housing to the west. Extensive stakeholder consultation and attention to visual impacts and adoption of CFA piling and off site prefabrication of the structure significantly reduced nuisance to neighbours.

Ground contamination in the substrate gave rise to the installation of a gas membrane under the structure and incorporation of ground water monitoring points within the site. The adjacent canal was a sensitive receptor and monitoring continued throughout construction and post completion.

All waste material was recycled through the Olympic Park on-site recycling centre. The MSCP achieved 98% recycling of site waste. Off site prefabrication techniques reducing waste and construction time, and enabled “deconstructability” after the Games and at the end of service life.

Materials used to construct the MSCP incorporated 21% recycled material content and 100% of bulk fill and sub-base were sourced from recycled or reused material. The groundworks included on-site lime stabilisation of existing soil to reduce bulk fill movements.

The structure’s post occupation energy use is limited to lighting, which has high efficiency luminaires and daylight sensor switching control. Photovoltaic panels are to be installed on the roof after the Games as part of ODA’s Games and Legacy sustainable energy strategy.

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

Meadow Lane Waterfront Regeneration

Meadow Lane Waterfront Regeneration

Over a five year period there has been quality improvements to the Nottingham Beeston Canal towpath where pedestrian counters and ...
Glenconway Wind Farm
| CEEQUAL Case Studies, Energy, UK

Glenconway Wind Farm

The Glenconway Wind Farm was developed by Gael Force Renewables Ltd, a Joint Venture between McLaughlin & Harvey, Barr and ...
Eastern Bay Link

Eastern Bay Link

The Eastern Bay Link scheme extends the A4232 link road, situated south of Cardiff, reducing the current journey by 2.5 ...
Foryd Harbour Public Realm

Foryd Harbour Public Realm

The Rhyl Harbour project formed part of a stream that included a sustainable transport bridge, coastal erosion and flood protection ...
Crossrail: Connaught Tunnel and Surface Railway | CEEQUAL
| CEEQUAL Case Studies, Rail, UK

Crossrail: Connaught Tunnel and Surface Railway

The Connaught Tunnel Refurbishment Project transformed an abandoned 1878 Victorian tunnel and disused railway and re-engineered it to receive the ...
Colwyn Bay: Phase 1 – Flood Defence | CEEQUAL

Colwyn Bay: Phase 1 – Flood Defence

The coastal defences along the Colwyn Bay frontage had several key issues to address through developments and improvements. As a ...

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags