Newcastle Wastewater Treatment Works

Newcastle WwTW project represents one of the most challenging wastewater facility upgrades to be undertaken for the client Northern Ireland Water in recent years.

CEEQUAL Excellent (80.7%) – Whole Project Award
Version 4, September 2017 | Newcastle, Northern Ireland

Client: Northern Ireland Water
Designer: DAWSON-WAM / Ovivo Joint Venture
Contractor: DAWSON-WAM / Ovivo Joint Venture

Assessors: Peter Kerr (DAWSON-WAM Ltd)

Project Summary

Newcastle WwTW project represents one of the most challenging wastewater facility upgrades to be undertaken for the client Northern Ireland Water in recent years.

Situated on the coastline of the Irish Sea and overlooked by the majestic Mourne Mountains, this upgrade represented a major investment by NI Water to improve the standard of discharge and quality of bathing waters in this popular seaside town.

Challenged with constructing a complex build, extending 2,000m2 into the Irish Sea, we would design and create a completely watertight area to facilitate construction and furthermore protect the surrounding Murlough Area of Outstanding Natural Beauty and Mourne Coast Area of Special Scientific Interest.

Creating a cofferdam, initially a stone bund was formed within a geotextile envelope, surrounded by rock armour to protect the works from the Irish Sea’s winter gales, flash floods and high tides. Sheet piled wall was driven through bund into bedrock to cut off water flow. A battery of pumps ensured that the tidal groundwater was forwarded to silt traps and settlement lagoon for filtering before returning to the sea.

Aspirations for a “Green Roof” saw consultation with local heritage and conservation groups to deliver a herb-rich maritime grassland, rich in biodiversity, spanning the entire roof area. This low maintenance native vegetation continues to provide a natural habitat for birds and insects. Safe-guarding this legacy maintenance contract was extended to 5-7 years. Wildlife habitat further enhanced through construction of bird ledges for Kittiwakes, shelters for Guillemots, otter holt, bat box and insect habitat.

Other key achievements saw all excavated material including excavated rock and breakwater rock armour reused in works or exported to other construction projects. Further opportunities to improve water quality in the area saw significant additional upgrade works to the contract period.

Gallery

People and Communities

Partnership links were established with key interest groups early in the contract including Mourne Trust Volunteers, Wild sea swimmers group, Harbour Regeneration Group.

On a voluntary basis the site was registered with the Considerate Constructors Scheme, providing the public with the opportunity to assess how we delivered the works within the neighbourhood. Project received National Bronze Award. As a Company Partner within the Scheme the site also received a National Silver Award, with “Excellent” scores for appearance and maintaining good relations with the local community.

Other achievements include an ICE Northern Ireland Sustainability Award and Finalists in CEF Construction Excellence Awards.

Ecology and Biodiversity

Aspirations from the Project Team for a “Green Roof” saw consultation with local heritage and conservation groups to deliver a herb-rich maritime grassland, spanning the entire roof area.

Working with local landscape experts from the County Down area and members of the Mourne Heritage Trust (MHT), the team devised a low-maintenance landscape plan that would be rich in biodiversity.

Using a special process known as hydroseeding, the top of the new 50m-long concrete structure was sown out with a special mix of indigenous coastal seeds to provide a low maintenance native vegetation green area, which not only offers a more attractive view for the overlooking properties, but which also provides a natural habitat for local birds and insects.

Safe-guarding this legacy maintenance contract was extended to 5-7 years.

Habitat for seabirds and local wildlife further enhanced through construction of bird ledges for Kittiwakes on the seaward side of the building, bird shelters for Guillomots resourcefully constructed from recycled drainage pipes & manholes within new rock armour, otter holt, bat box and insect habitat.

The Water Environment

Challenged with constructing a complex build, extending 2,000m2 into the Irish Sea, we would design and create a completely watertight area to facilitate construction and furthermore protect the surrounding Murlough Area of Outstanding Natural Beauty and Mourne Coast Area of Special Scientific Interest.

Creating a cofferdam, initially a 250m long stone bund was formed within a geotextile envelope, surrounded by 13,000 t’s of rock armour to protect the works from the Irish Sea’s winter gales, flash floods and high tides. 210 lm sheet piled wall was driven 14m through bund into bedrock to cut off water flow. A battery of pumps ensured that the tidal groundwater was forwarded to silt traps and settlement lagoon for filtering before returning to the sea.

Physical Resources – Use and Management (Energy, Water, Materials Waste)

Other key achievements saw all excavated material including 2,000t excavated rock and 13,000t breakwater rock armour reused in works or exported to other construction projects.

Further Details

Accepting the award on behalf of the project team, Kieran Grant, NI Water’s Project
Manager for the scheme said:

This £10m project represents one of the most complex wastewater facility upgrades to be undertaken for NI Water in recent years. Located on the County Down coast, in one of NI’s top seaside resorts, the Newcastle Wastewater Treatment Works Project presented NI Water and its contractor, Dawson-Wam Ovivo JV with numerous civil engineering, environmental and aesthetic challenges, all of which were overcome on a highly successful project fully embraced by client and contractor alike. We are delighted to receive this prestigious award which is a fitting tribute to the efforts of the entire design and construction team.

Award Presentation

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

Eastern Bay Link

Eastern Bay Link

The Eastern Bay Link scheme extends the A4232 link road, situated south of Cardiff, reducing the current journey by 2.5 ...
Foryd Harbour Public Realm

Foryd Harbour Public Realm

The Rhyl Harbour project formed part of a stream that included a sustainable transport bridge, coastal erosion and flood protection ...
Crossrail: Connaught Tunnel and Surface Railway | CEEQUAL
| CEEQUAL Case Studies, Rail, UK

Crossrail: Connaught Tunnel and Surface Railway

The Connaught Tunnel Refurbishment Project transformed an abandoned 1878 Victorian tunnel and disused railway and re-engineered it to receive the ...
Colwyn Bay: Phase 1 – Flood Defence | CEEQUAL

Colwyn Bay: Phase 1 – Flood Defence

The coastal defences along the Colwyn Bay frontage had several key issues to address through developments and improvements. As a ...
Bulford Road Improvement Scheme | CEEQUAL

Bulford Road Improvement Scheme

The Bulford Road Improvement project was conceived and designed to provide significant improvements to a single lane road between the ...
Baltic Triangle Public Realm Improvements

Baltic Triangle Public Realm Improvements

The Baltic Triangle scheme was formulated to implement improvements to the public realm in the creative industries location of the ...

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags