Hitchin Grade Separation | CEEQUAL

Hitchin Grade Separation

Hitchin Grade Separation | CEEQUAL

CEEQUAL Excellent (82.9%) – Design & Construction Award
Version 5, Nov 2015 | Hitchin, England

ClientNetwork Rail
DesignerTony Gee & Partners
ContractorHOCHTIEF (UK) Construction
Assessor: Derek Walter (HOCHTIEF), Julian Gregory (Ecovigour)

Project Summary

This project was conceived by Network Rail over 15 years ago to improve timetables on the East Coast Main Line (ECML) where the Cambridge line traffic crossed the ECML on a flat crossing. The Cambridge Junction Grade Separation Project (now identified as the “Hitchin Alliance”) takes the Down Cambridge line over the ECML via embankments and viaducts, to rejoin with the existing Cambridge route approximately 1.5km east of Hitchin.

The project involved the construction of the new elevated route via imported fill embankments and an elevated rail flyover extending over 800m and comprising steel girders and concrete deck. At either end of the grade separation new junctions were formed to align with the existing railway and included modifications to the Overhead Lines, Signalling and Telecoms. The project also delivered the new railway i.e. track, overhead line, signalling, power and telecommunications over the new route.

Hitchin Grade Separation | CEEQUAL
Image: © Marcus Daws

Achievements

Collaborative working in a ‘Pure Alliance’

Part way through the tender process, the Client introduced the concept of awarding the Contract as a ‘Pure Alliance’. This involved Contractor and Client teams fully integrating, co-locating and working under a modified NR12 contract to reflect the alliancing ethos.

The Hitchin Alliance was formed using the BS11000 ‘collaborative business relationship management’ standard and principles. This was a ‘demonstration project’ for Network Rail, amongst the first of its kind, so the process was closely scrutinised by Network Rail executives, meaning by definition an open an honest approach was needed to succeed, which is a quality HOCHTIEF prides itself upon.

Headed by the Alliance Manager, the Alliance Integrated Project Organisation was designed to seek economy in resources by fully integrating team members from both parent companies and key suppliers. Team leaders from several disciplines formed the Alliance Leadership team. Their role was to take responsibility for identifying and managing change and risk, driving economy and innovation and ensuring that the project achieved or surpassed the key outputs. As the Alliance had ownership of the majority of project risks and opportunities there was a combined and committed desire to ensure that the process was robustly managed and that the Alliance achieved the maximum benefit.

One of the key outputs of a ‘Pure Alliance’ is to drive innovation through the whole project lifecycle. The Hitchin Project delivered GRIP stages 5-8, therefore innovations were targeted on detailed design and delivery. Value engineering and design workshops were initiated from the outset with designers, reviewers and approvers forming a single integrated team. This allowed the opportunities to be established, developed and determined efficiently. The mutual benefit from this ensured that all parties worked together to drive initiatives to a conclusion.

Hitchin Grade Separation | CEEQUALHitchin Grade Separation | CEEQUALHitchin Grade Separation | CEEQUAL
Image: © Network Rail

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

Paddington Bakerloo Line Link
| CEEQUAL Case Studies, Rail, UK

Paddington Bakerloo Line Link

The complex £40 million Bakerloo Line Link project provides a new 170m pedestrian tunnel link between the Paddington Crossrail Station ...
Leigh to Ellenbrook Guided Busway

Leigh to Ellenbrook Guided Busway

The Leigh to Ellenbrook guided busway is a 4.5 mile dual track bus rapid transit system. It provides bus infrastructure ...
Hitchin Grade Separation | CEEQUAL
| CEEQUAL Case Studies, Rail, UK

Hitchin Grade Separation

This project was conceived by Network Rail over 15 years ago to improve timetables on the East Coast Main Line ...
Bygrave Anaerobic Digestion Plant | CEEQUAL
| CEEQUAL Case Studies, Energy, UK

Bygrave Anaerobic Digestion Plant

The £12m anaerobic digestion (AD) plant at Bygrave Lodge Farm, near Baldock in Hertfordshire was developed as part of Biogen’s ...
Mosjøen Harbor Remediation | CEEQUAL

Mosjøen Harbor Remediation

Mosjøen Harbor Remediation includes dredging of contaminated sediment and placement of this sediment in steel sheetpile cells (CDF) for an ...
Bornsjöverket

Bornsjöverket

Bornsjön is a water conservation area and Stockholm Water and waste reservoir. The main objective of the project was to ...

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags