Greyabbey and Kircubbin Wastewater Treatment Works

Greyabbey and Kircubbin Wastewater Treatment Works | CEEQUAL

CEEQUAL Excellent (91.9%) – Whole Team Award
Version 2, June 2003 | Kircubbin, Northern Ireland

ClientNorthern Ireland Water Service
DesignerNorthern Ireland Water Service
ConstructionGeda and EPS Consortium
Assessor: Neil Brady

Project Summary

Greyabbey and Kircubbin are located towards the northern end of Strangford Lough, Northern Ireland. In 2001 Water Service Design Group undertook the task of designing 2 new Waste Water Treatment Works for the area: one on the existing site at Greyabbey and the other at a new site at Monaghan Bank, Kircubbin. The design included the most up to date process technology – Membrane Biological Reactors. Construction started on the Kircubbin site in April 2002 and at Greyabbey in June 2002. The contract was awarded to Geda Construction Ltd and EPS (Ireland) Ltd in consortium. Both sites were commissioned in August 2003.

As Strangford Lough is an Area of Outstanding Natural Beauty, Area of Special Scientific Interest, and has a high environmental, cultural and heritage value with various bird and nature reserves, Water Service considered the potential effects of the construction on the appearance of the area as a whole, the effects on the ecologically sensitive surroundings and the effect on the local community. All of this had to be achieved within a tight budget.

With these in mind the project constructed two ‘state of the art’ Wastewater Treatment works, housed in buildings which reflect the surrounding area in the choice of material, finished in basalt style cladding and slate effect roof, landscaped with indigenous plants and shrubs where the land had been previously agricultural fields or concreted areas. The local community was also considered with a high PR effort. Over the last 3-4 years Water Service representatives have given presentations and held discussions with council members, community representatives and members of numerous local nature and wildlife organisations. The project has taken on board feedback from these sessions and has tried to incorporate ideas, where possible, into the scheme. The contract used the NEC conditions of contract and was completed on time and to budget.

It was due to the high attention of detail to the environmental, cultural and heritage, community relations and land use issues that achieved the CEEQUAL award. To date it is the highest scoring project in the UK, obtaining a result of 91.9% – well into the Excellent Category.

Gallery

Greyabbey and Kircubbin Wastewater Treatment Works | CEEQUAL

 

Greyabbey and Kircubbin Wastewater Treatment Works | CEEQUAL

 

 

Greyabbey and Kircubbin Wastewater Treatment Works | CEEQUAL

 

Greyabbey and Kircubbin Wastewater Treatment Works | CEEQUAL

 

 

Greyabbey and Kircubbin Wastewater Treatment Works | CEEQUAL

 

Greyabbey and Kircubbin Wastewater Treatment Works | CEEQUAL

 

 

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

Dover Western Docks Revival (DWDR) – Port of Dover | CEEQUAL

Dover Western Docks Revival (DWDR) – Port of Dover

Dover Western Docks Revival (DWDR) is a one-off opportunity for the regeneration of Dover, bringing new investment into the area ...
Read More
M4 Junction 28 Improvements | CEEQUAL

M4 Junction 28 Improvements

The improvement of the junction is seen by the Welsh Government as an important part of its programme for economic ...
Read More
Blue line to Barkarby Access tunnel Robothöjden-Landningsbanan

Blue line to Barkarby Access tunnel Robothöjden-Landningsbanan

The project achieved a CEEQUAL Excellent rating. CEEQUAL enabled more discussions in the project group about sustainability which lead to ...
Read More
Rv3/Rv25 new highway between Loten-Elverum

Rv3/Rv25 new highway between Loten-Elverum

The main savings in the project as a result of implementation of CEEQUAL is related to transport and reuse of ...
Read More
Blue line to Barkarby Access tunnel Veddesta

Blue line to Barkarby Access tunnel Veddesta

The client’s drivers were primarily to use Ceequal as a tool to constantly improve the environmental and sustainability work and ...
Read More
Newcastle Wastewater Treatment Works

Newcastle Wastewater Treatment Works

Newcastle WwTW project represents one of the most challenging wastewater facility upgrades to be undertaken for the client Northern Ireland ...
Read More

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags