Glencorse Water Treatment Works Part 2

Glencorse 1 | BRE Group

CEEQUAL Excellent (84.5%) – Whole Project Award + Interim
Version 4, Dec 2011 | Penicuik, Scotland

Winner of a CEEQUAL Outstanding Achievement Award 2013 for Community Relations

ClientScottish Water
DesignBDPBlack & Veatch and ERM
ConstructionBlack & Veatch
Assessor: Neil McCulloch

Project Summary

Scottish Water’s new Glencorse Water Treatment Works (WTW) is delivering 21st century drinking water to around 450,000 people across Scotland’s modern capital city. The works replaces two ageing facilities at Fairmilehead and Alnwickhill, which despite having served the city well for more than a century, now need replacing.

Combining engineering feasibility reports with the results of the largest ever community consultation in Scottish Water’s history the site at Glencorse in Midlothian was chosen for the project to take place.

Capable of supplying Edinburgh with up to 175-million litres of clear, fresh drinking water everyday, the Glencorse project has sustainability at its core. A third of the works energy needs will be provided by an on-site hydro turbine. This is driven by the raw water which arrives from reservoirs in the Borders using gravity alone.

This raw water supply is treated beneath the largest ‘grass’ roof in Scotland, before being stored in a 90 million litre storage tank – one of the largest in Europe – and is delivered to customers across the city, again using gravity alone. Rain water harvested from the ‘grass’ roof is passed to bio-diverse wetlands that provide a rich habitat for indigenous plants, animals and insects.

Glencorse Water Treatment Works Part 2 | CEEQUAL

 

Influence of CEEQUAL

Considering CEEQUAL, Scottish Water and Black & Veatch introduced a world first, a mobile pipeline production unit. The plant was located next to the trunk main route allowing engineers to roll the pipes out of the factory and straight into the ground. This helped to save more than a million lorry miles and the associated carbon dioxide emissions.

Tunnelling underneath the Edinburgh City Bypass allowed work on the pipeline to progress without disturbing the thousands of commuters who use this vital artery every day.

Achievements

The Historic Environment

Following early archaeological investigations a Roman Marching Camp was discovered. Again neighbours were consulted to decide the relocation of the treatment building, preserving this historic site. This information was presented along with Cromwellian finds and evidence of a WWII Army Camp that was unearthed during excavations – resulting in 177 visitors to an Archaeological Open Day for Residents.

Waste Management

Spoil from initial excavation work was stored on site, to be used in landscaping the facility, blending it into the Pentland Hills. This helped to reduce construction traffic by 75%, making local roads safer. The use of recycled materials on-site also exceeded 25%.

Effects on Neighbours

Those residing round the WTW’s perimeter have been consulted throughout, providing input into the height and scale of final landscaping. Homeowners were even consulted on the location of individual trees providing final landscaping.

Award Presentation

Glencorse Water Treatment Works Part 2 | CEEQUAL

Glencorse Water Treatment Works Part 2 | CEEQUAL

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

Worcestershire Sustainable Infrastructure | BRE Group

Worcestershire Parkway Regional Interchange

Worcestershire Parkway is a new station at the intersection of the Worcester to London (OWW line) and Birmingham to Bristol ...
Read More
BREEAM Infrastructure Version 6 for Projects Construction E16 Eggemoen Olum E02 Åsbygda Olum | BRE Group

E16 Eggemoen-Olum, E02 Åsbygda-Olum

Skanska won a  contract from the Norwegian public Roads Administration in 2019 to build 10.4 km of new E16 road ...
Read More
Sege Park Sustainable Infrastructure | BRE Group

Urban development project Sege Park

Sege Park urban development project is an urban development and regeneration project in Malmö. A former hospital area is being transformed ...
Read More
light rail sustainable and safer city Bybanen Bergen | BRE Group

Bybanen D11 Sentrum

To achieve a more sustainable and safer city, Bybanen Bergen, are building a light rail. The first phase of the ...
Read More
Lillestrøm pumping station | BRE Group

Pumpestasjon PA240 – Lillestrøm Kommune

Construction of a new pumping station infrastructure in the municipality of Lillestrøm. The project has great social significance in terms ...
Read More
Westside Metro Extension Phase One | BRE Group

Birmingham Westside Metro – Centenary Square Extension

The Midland Metro Alliance (MMA) is working on behalf of Transport for West Midlands (TfWM), which is part of the ...
Read More

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags