7 Black Cart Cycleway Bridge - Installed

Glasgow Airport Investment Area Leads in Sustainable Infrastructure Innovation

7 Black Cart Cycleway Bridge - Installed

CEEQUAL Excellent – Construction Only Assessment

Version 6, 2022 | Glasgow, UK

Assessed by: Stuart Angus Wills Bros Civil Engineering Ltd
Verified by: Keira McLuskey Network Rail
Client: Renfrewshire Council
Contractor: Wills Bros Civil Engineering Ltd

Project Summary

The Glasgow Airport Investment Area (GAIA) project creates the connections and infrastructure underpinning the development of Scotland’s manufacturing innovation district. It includes new roads, bridges, cycling routes and pedestrian footpaths, which will connect the Advanced Manufacturing Innovation District Scotland (AMIDS) and the nearby Westway and Inchinnan Business Parks.

The £39.1million Glasgow City Region City Deal funded GAIA project will support the AMIDS which in turn will bring new employers, jobs and opportunities to the City Region and ensure the continued success of Glasgow Airport.

Key features of the project:

• Abbotsinch Road has been realigned, upgraded, and extended, with accompanying pedestrian and cycle facilities to create a route through Netherton Campus, the central site of the manufacturing district.

• A two-lane bridge for pedestrians, cyclists and commercial traffic across the White Cart River from an approach road off Arran Avenue to Wright Street. The bridge includes a connection into Wright Street business premises, with no through route along Wright Street for vehicles. This reduces the impact of traffic on residential areas and the bridge also connects with the proposed Paisley to Renfrew cycle route, currently under development.

• A 100m long, single-span pedestrian and cycle bridge over the Black Cart, connecting Abbotsinch Road to Greenock Road. Installation of the 160-tonne steel structure was undertaken by tandem crane lift during an overnight airport closure due to the proximity to the runway.

• New and improved junctions and connections to existing cycling and pedestrian routes.

• An innovative lightweight protection structure for a series of fragile high voltage cables which substituted reinforced concrete piles and beams with 6000 recycled plastic geocellular crates and lightweight ‘LECA’ fill material.

• Over 330 extra heavy standard and semi-mature trees planted on the scheme to create an attractive avenue-style environment along the realigned road.

 

Black Cart Cycleway Bridge - Tandem Crane Lift

Metrics

Embodied carbon emissions 12,435 kg CO2 equivalent 20% reduction achieved
Operational renewable energy potential 1,656 kWh per year 5% of total energy use
Re-used material 31558 m3 55% of total material excavated
Waste diverted from landfill N/A tonnes or m3 100% of total inert/non-haz waste

Financial Benefits

In your view, has CEEQUAL represented value for money?

Yes. Whilst we weren’t able to quantify any financial benefits, CEEQUAL provided a framework which encouraged sustainable decision-making in the construction phase of the project.

 

Wright St Link Bridge - Precast Beam Installation

Achievements

100% of non-hazardous wastes were diverted from landfill and either reused, recycled or used to generate waste derived fuels.

20% reduction in carbon emissions achieved when compared to baseline.

 

Vertical Drainage Installation sustainable infrastructure

Further Information

What were the main challenges for the project and how were these overcome?

Dealing with very poor ground conditions under the footprint of the new road. This required the use of vertical drains, observation of settlement periods and the use of geogrids to achieve a solid foundation.

Drainage Attenuation Tank Installation

What were the drivers and perceived benefits for undertaking a CEEQUAL assessment on this project?

There was a greater focus on opportunities to minimise waste and maximise resource efficiency than there would likely have otherwise been.

What elements of this project highlight best practice and innovation?

The innovative cable protection structure eliminated huge quantities of reinforced concrete and replacing them with recycled plastic and air.

 

132kV Lightweight Embankment Installation

Quotes

“By undertaking a CEEQUAL assessment we gave ourselves a reason to bring together key members of the project team at regular intervals and challenge them to think about sustainability as part of their day-to-day decision-making on things such as methods of working and material selection.”

Stuart Angus – Design & Sustainability Manager, Wills Bros (Contractor)

BREEAM Infrastructure insights and case studies

Browse the latest insights, thinking and case studies from BREEAM Infrastructure

 

Ramsdal bridge BREEAM Infrastructure

E39 Mandal øst – Mandal

E39 Mandal East- Mandal city consist of a 7 km long four lane highway that together with the new E39 ...
BREEAM Infrastructure Bybanen D18 Sykkelvei Kronstadtunnelen

Bybanen D18 Sykkelvei Kronstadtunnelen

Project D18 Sykkelvei Kronstadtunnelen is part of the Bybanen-light rail construction stage 4 development scheme. This is the largest development ...
Sustainable Rail construction Leeds Station

Transpennine Route Upgrade (TRU) Leeds Station Capacity

Leeds Station Capacity is the first project to be completed as part of the TRU programme. All TRU projects are ...
BREEAM-Infrastructure-sustainable-Bergen-Norway-underground-station-platforms

Bybanen D13 Haukeland Holdeplass

Bybanen D13 Haukeland Holdeplass is the very first underground station at the light rail system in Bergen, Norway.  It has ...
A77 Maybole bypass southern roundabout sustainable infrastructure

A77 Maybole Bypass Construction Award

The A77 Maybole Bypass reduces journey times on the A77 by diverting traffic away from the High Street of the ...
Drone Photo of new jetty at Thanckes Oil Fuel Depot

Thanckes Oil Fuel Depot Loading Facility & Tank Farm Fire Fighting Upgrade

VolkerStevin constructs a new jetty at Thanckes Oil Fuel Depot to provide fuelling facilities for the Royal Navy at Devonport ...

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how BREEAM Infrastructure can support you.