Crossrail: Connaught Tunnel and Surface Railway | CEEQUAL

Crossrail: Connaught Tunnel and Surface Railway

Crossrail: Connaught Tunnel and Surface Railway | CEEQUAL

CEEQUAL Excellent (86.7%) – Whole Project Award
Version 4, Apr 2015 | London, UK

ClientCrossrail Ltd
DesignerAtkins
ContractorVINCI Construction UK Ltd
Assessors: Mike de Silva (Crossrail), Paul Sandall (Vinci Construction), Ghinwa Chammas (Atkins)

Project Summary

The Connaught Tunnel Refurbishment Project transformed an abandoned 1878 Victorian tunnel and disused railway and re-engineered it to receive the Crossrail track and trains for the next 120 years. The project was technically challenging and very unusual for a major new transport scheme such as Crossrail.

The principal elements of the Project comprised:

  • Refurbishment and modification to the existing Connaught Tunnel and approach ramps, including converting the twin binocular tunnels into one large-bore tunnel, requiring the central section to be removed and rebuilt by ‘cut and cover’ method enabled by two cofferdams in the dock allowing dewatering.
  • Construction of the surface rail between Custom House Station and North Woolwich portal.
  • Upgrading drainage systems.
  • Micro tunnelling / SCL works in pump house and vent shafts.
  • Demolition of buildings which included Grade Listed Buildings.
  • Marine Works / Diving Operations.

 

CEEQUAL was used to influence and in turn assess the sustainability of the Project. The Project achieved an ‘Excellent’ CEEQUAL Whole Project Award. There were a number of key areas where the Project scored particularly highly.

Crossrail: Connaught Tunnel and Surface Railway | CEEQUAL
© Crossrail Ltd.
Crossrail: Connaught Tunnel and Surface Railway | CEEQUAL
© Crossrail Ltd.
Crossrail: Connaught Tunnel and Surface Railway | CEEQUAL
© Crossrail Ltd.

Challenges and Achievements

Water Environment

The Connaught Tunnel was considered to be one of Crossrail’s highest risk sites from an environmental perspective given its direct interface with the London Docks. The continuous protection measures put in place over the length of the Project helped the Project Team to secure an ‘Excellent’ CEEQUAL rating in this category. The training and protection measures put in place ensured no major pollution incidents took place over the length of the Project. One key measure was spill training for operatives. Every operative who came onto the site was fully trained and briefed on how to operate the mechanisms within the tunnel which would divert the water flow from the London Docks into the sewer. Further to this, all the water flowing into the tunnel came through two attenuation tanks, both of which had oil spill absorbents within them, allowing operatives to mitigate this environmental risk.

 

Crossrail: Connaught Tunnel and Surface Railway | CEEQUAL
© Crossrail Ltd.

People & Communities

The Project Team also scored very highly in the People & Communities section. The Project made use of a community liaison representative who ran a number of initiatives over the Project. Initiatives included:

  • Frequent charitable donations to the local school, including both financial and resource support for any campaigns the school was running.
  • A book buddies initiative whereby staff would read to pupils.
  • Repainting the local community centre.
  • Donating surplus materials to help local volunteers building a community garden and sponsorship of local business.

Design Changes

During the initial stages of the Project, the Project Team were able to propose design changes, many of which brought a considerable environmental benefit in addition to cost savings. The following, amongst many others, were design changes proposed that brought about environmental benefits as well as cost savings:

Instrumentation and Monitoring

The instrumentation and monitoring system was redesigned reducing the number of monitoring points. It used automated systems where possible. — Nearly £1m saving

  • Reduction in site visits by technical staff (transport)
  • Removing night works removed the need for task lighting (energy, night lights) and removed noise from working at night
Piling

The original proposed piling method from Crossrail was VCC Piling. This was changed to Controlled Modulus Column piling. — £300K saving

  • Faster method which reduced deliveries/ visits to site
  • Less noise and vibration impacts
  • Reduced diameter of piles (450mm – 320mm) so reduction in materials and reduction in deliveries
Vehicle Restraint Wall

Vehicle restraint wall combined into track slab so a wall “toe” was no longer required. — £250K saving

  • Reduction in materials including reinforcement and concrete
  • Reduction in deliveries (transport)
  • Reduced scope meant reduced temporary works so no additional excavations, trench sheets required (materials and plant use)
  • Removed requirement for remobilisation (equipment deliveries etc.)
Reuse of Track Ballast

Track ballast on site reused in load transfer platform. — £100K saving

  • Reduction in material sent off site (transport)
  • Reduction in materials delivered (transport)
  • Reduction in waste sent off site
  • Increased proportion of on-site recycled material
Dewatering System

Change to dewatering scheme reduced the number of deep wells into chalk aquifer and the injectors were installed from the tunnel, rather than from the surface. — £185K saving

  • Reduction in pathways for contamination
  • Less community disruption to surface from drilling
  • Less noise and vibration and air quality impacts on the surface as no drilling at that location
Silt Removal

Silt removal changed to silt displacement. — £50K saving

  • Reduction in equipment required: silt curtains, fish scarers, booms across dock and boats etc.
  • Reduction in ecological impact and risk of impacting fish etc
Crossrail: Connaught Tunnel and Surface Railway | CEEQUAL
© Crossrail Ltd.

How did CEEQUAL Influence the Project?

The CEEQUAL assessment was a key factor in the project achieving its sustainability goals from beginning to end. The nature of CEEQUAL meant sustainability was considered and looked at through each stage of the project, from design, through to an interim assessment in the midst of construction, and to the final review at the end of the project.

CEEQUAL influenced the design in order to fulfil the goal of attaining a CEEQUAL ‘Excellent’ Award. When construction had come to an end, the contractor VINCI Construction UK, and client Crossrail, came together to look over the whole life of the project, collating and discussing sustainability achievements. This shows how CEEQUAL can bring different parts of the project team closer together as they come together to achieve a joint award.

Crossrail: Connaught Tunnel and Surface Railway | CEEQUAL
© Crossrail Ltd.

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

River Lagan Dredging Works | CEEQUAL
| CEEQUAL Case Studies, Flood Alleviation, UK

River Lagan Dredging Works

The site of the dredging works was the River Lagan which flows through the middle of Belfast. The dredging works ...
Dundee Central Waterfront: Contract 4 | CEEQUAL

Dundee Central Waterfront: Contract 4

The transformation of Dundee’s waterfront reached a major milestone at the end of February 2016 with the opening to the ...
Crossrail Surface Works: Stockley Flyover | CEEQUAL
| CEEQUAL Case Studies, Rail, UK

Crossrail Surface Works: Stockley Flyover

Stockley Flyover is a £90 million Crossrail Project and after number of years of construction is almost complete. The objective ...
Crossrail: Eleanor Street & Mile End Road Shafts
| CEEQUAL Case Studies, Rail, UK

Crossrail: Eleanor Street & Mile End Road Shafts

Crossrail is delivering the Elizabeth line – a new railway for London and the South East. When it opens through ...
Colwyn Bay Waterfront Project – Design of Vibrant and Viable Places (VVP) Phase 2 Promenade Enhancements | CEEQUAL

Colwyn Bay Waterfront Project – Design of Vibrant and Viable Places (VVP) Phase 2 Promenade Enhancements

This project represents Phase 2 of the Colwyn Bay Waterfront Project, a major scheme delivered by Conwy County Borough Council ...
Crossrail: Whitechapel and Liverpool Street SCL | CEEQUAL
| CEEQUAL Case Studies, Rail, UK

Crossrail: Whitechapel and Liverpool Street SCL

Crossrail C510 Whitechapel and Liverpool Street Station Tunnels is a major tunnelling contract awarded as part of Crossrail, Europe’s largest ...

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags