Colwyn Bay: Phase 1 – Flood Defence | CEEQUAL

Colwyn Bay: Phase 1 – Flood Defence

Colwyn Bay Phase 1 Flood Defence Featured Image 01 BRE Group

CEEQUAL Very Good – Whole Project Award
Version 4, Aug 2014 | Colwyn Bay, Wales, UK

ClientConwy County Borough Council;
DesignerMott MacDonald;
ContractorVolkerStevin;
Assessor: Hazel Weston (URS);
Verifier: Perry Shard (Balfour Beatty);

Project Summary

The coastal defences along the Colwyn Bay frontage had several key issues to address through developments and improvements. As a result of regular over-topping of the defences, the defences themselves were being negatively impacted, as well as local infrastructure, and the local community through the regular closing of the coast road after storm damage. The ageing and deteriorating defences had an imminent risk of failure if they were left in situ.

Work on the defences was divided into phases – this assessment covers the phase 1 works at the eastern end of the bay, opposite Erias Park. Work included construction of a rock groyne, rock and pre-cast concrete step revetments, creation of a permanent beach, and an extension to the existing promenade in the area. The platform created by the promenade extension had concrete piles installed which were used for the construction of the new water sports building which has a viewing area on the roof, and links into the upgraded promenade with cycle lanes and landscaped areas.

Eventually the whole of the bay will be developed, with renewed sea defences and integrated environmental improvements along the promenade. There will also be environmental regeneration improvements to the promenade to offer a usable and safe and sustainable public realm space. This first phase of works is the platform for the whole project.

Colwyn Bay: Phase 1 – Flood Defence | CEEQUAL
Beach and rock groyne
Colwyn Bay: Phase 1 – Flood Defence | CEEQUAL
Aerial view of Colwyn Bay and the developments to the Bay’s frontage

Challenges and Achievements

Material Use

Colwyn Bay: Phase 1 – Flood Defence | CEEQUAL
Sand being laid to create beach profile

The nature of the works mean that a lot of material has been brought on to site to build up the beach and rock groynes. In order to make this as sustainable as possible, comprehensive policies were written into the Environmental Statement which was produced in the early planning stages highlighting issues such as reusing existing boulders, prioritising local suppliers and transporting sand for the beach recharge to the site via the sea.

During the design stage it was confirmed that all timber purchased by VolkerStevin (the contractor), their subcontractors, or their suppliers would be legal, sustainable, and FSC/PEFC certified. The Armourstone was sourced from local quarries, the class 6A, 6F1 and 6P material was sourced locally from Menmaenmawr, and the Hauraton Environkerb was constructed from recycled material as an alternative to the ACO Kerbdrain system. In addition, 100% of the existing structures on site were incorporated into the design.

Ecology and Biodiversity

 

The new flood defence structures included in the design will encourage new marine habitats to develop over time. In addition, the new groyne structures and sand recharge will create a new ocean habitat – these have been witnessed in situ – photos are available on request. The sand may provide valuable new habitat for the BAP species, Mytilus edilus (Blue mussel).

Bioblocks are also incorporated into the groyne structure to encourage and monitor habitat growth.

How Did CEEQUAL Influence Your Project?

Colwyn Bay: Phase 1 – Flood Defence | CEEQUAL
New beach at Colwyn Bay

Sustainability has been integral to the whole Waterfront project and has been taken into account right from the start. Conwy County Borough Council stated that a ‘very high level of environmental performance was to be a key aspect of the Colwyn Bay Waterfront Development project’. The flood defence and infrastructure works aimed to achieve a CEEQUAL target of at least Very Good.

A high level sustainability review was carried out to investigate potential risks and opportunities. A CEEQUAL pre-assessment was carried out which included verbal discussions with the client as to what issues were to be targeted and which were not likely to be achieved. When the designer and contractors were both appointed further CEEQUAL reviews were carried out to ensure that both were fully aware of the requirements of the assessment and the types of evidence that would be required. It was important that the team did not have to produce CEEQUAL specific information, rather the drawings and reports that were being produced as part of the project were suitable. By introducing CEEQUAL early in the project, the project has managed to achieve its target of Very Good.

 

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

Sea filling winter conditions BREEAM Infrastructure BRE Group

E16 Kvamskleiva

E16 Kvamskleiva was mainly a rock slide protection project in an area with steep mountain sides and frequent ice and ...
Read More
Flomsikring Mjøndalen sentrum Vassenga03 BRE Group

Flomsikring Mjøndalen sentrum – Vassenga

Flomsikring Mjøndalen - Vassenga is part of the flood defence project in Mjøndalen, aiming to reduce the flood risk in ...
Read More
Norway Audnadalen Artist Wichada Treepoonpon Sweco Norge BRE Group

E39 Mandal – Lyngdal øst

Nye Veier AS have, in collaboration with Sweco Norge AS, planned a new four-lane motorway from Mandal River through Lindesnes ...
Read More
Worcestershire Sustainable Infrastructure BRE Group

Worcestershire Parkway Regional Interchange

Worcestershire Parkway is a new station at the intersection of the Worcester to London (OWW line) and Birmingham to Bristol ...
Read More
BREEAM Infrastructure Version 6 for Projects Construction E16 Eggemoen Olum E02 Åsbygda Olum BRE Group

E16 Eggemoen-Olum, E02 Åsbygda-Olum

Skanska won a  contract from the Norwegian public Roads Administration in 2019 to build 10.4 km of new E16 road ...
Read More
Sege Park Sustainable Infrastructure BRE Group

Urban development project Sege Park

Sege Park urban development project is an urban development and regeneration project in Malmö. A former hospital area is being transformed ...
Read More

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags