Colwyn Bay: Phase 1 – Flood Defence | CEEQUAL

Colwyn Bay: Phase 1 – Flood Defence

Colwyn Bay Phase 1 Flood Defence Featured Image 01 | BRE Group

CEEQUAL Very Good – Whole Project Award
Version 4, Aug 2014 | Colwyn Bay, Wales, UK

ClientConwy County Borough Council;
DesignerMott MacDonald;
ContractorVolkerStevin;
Assessor: Hazel Weston (URS);
Verifier: Perry Shard (Balfour Beatty);

Project Summary

The coastal defences along the Colwyn Bay frontage had several key issues to address through developments and improvements. As a result of regular over-topping of the defences, the defences themselves were being negatively impacted, as well as local infrastructure, and the local community through the regular closing of the coast road after storm damage. The ageing and deteriorating defences had an imminent risk of failure if they were left in situ.

Work on the defences was divided into phases – this assessment covers the phase 1 works at the eastern end of the bay, opposite Erias Park. Work included construction of a rock groyne, rock and pre-cast concrete step revetments, creation of a permanent beach, and an extension to the existing promenade in the area. The platform created by the promenade extension had concrete piles installed which were used for the construction of the new water sports building which has a viewing area on the roof, and links into the upgraded promenade with cycle lanes and landscaped areas.

Eventually the whole of the bay will be developed, with renewed sea defences and integrated environmental improvements along the promenade. There will also be environmental regeneration improvements to the promenade to offer a usable and safe and sustainable public realm space. This first phase of works is the platform for the whole project.

Colwyn Bay: Phase 1 – Flood Defence | CEEQUAL
Beach and rock groyne
Colwyn Bay: Phase 1 – Flood Defence | CEEQUAL
Aerial view of Colwyn Bay and the developments to the Bay’s frontage

Challenges and Achievements

Material Use

Colwyn Bay: Phase 1 – Flood Defence | CEEQUAL
Sand being laid to create beach profile

The nature of the works mean that a lot of material has been brought on to site to build up the beach and rock groynes. In order to make this as sustainable as possible, comprehensive policies were written into the Environmental Statement which was produced in the early planning stages highlighting issues such as reusing existing boulders, prioritising local suppliers and transporting sand for the beach recharge to the site via the sea.

During the design stage it was confirmed that all timber purchased by VolkerStevin (the contractor), their subcontractors, or their suppliers would be legal, sustainable, and FSC/PEFC certified. The Armourstone was sourced from local quarries, the class 6A, 6F1 and 6P material was sourced locally from Menmaenmawr, and the Hauraton Environkerb was constructed from recycled material as an alternative to the ACO Kerbdrain system. In addition, 100% of the existing structures on site were incorporated into the design.

Ecology and Biodiversity

 

The new flood defence structures included in the design will encourage new marine habitats to develop over time. In addition, the new groyne structures and sand recharge will create a new ocean habitat – these have been witnessed in situ – photos are available on request. The sand may provide valuable new habitat for the BAP species, Mytilus edilus (Blue mussel).

Bioblocks are also incorporated into the groyne structure to encourage and monitor habitat growth.

How Did CEEQUAL Influence Your Project?

Colwyn Bay: Phase 1 – Flood Defence | CEEQUAL
New beach at Colwyn Bay

Sustainability has been integral to the whole Waterfront project and has been taken into account right from the start. Conwy County Borough Council stated that a ‘very high level of environmental performance was to be a key aspect of the Colwyn Bay Waterfront Development project’. The flood defence and infrastructure works aimed to achieve a CEEQUAL target of at least Very Good.

A high level sustainability review was carried out to investigate potential risks and opportunities. A CEEQUAL pre-assessment was carried out which included verbal discussions with the client as to what issues were to be targeted and which were not likely to be achieved. When the designer and contractors were both appointed further CEEQUAL reviews were carried out to ensure that both were fully aware of the requirements of the assessment and the types of evidence that would be required. It was important that the team did not have to produce CEEQUAL specific information, rather the drawings and reports that were being produced as part of the project were suitable. By introducing CEEQUAL early in the project, the project has managed to achieve its target of Very Good.

 

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

light rail sustainable and safer city Bybanen Bergen | BRE Group

Bybanen D11 Sentrum

To achieve a more sustainable and safer city, Bybanen Bergen, are building a light rail. The first phase of the ...
Read More
Lillestrøm pumping station | BRE Group

Pumpestasjon PA240 – Lillestrøm Kommune

Construction of a new pumping station infrastructure in the municipality of Lillestrøm. The project has great social significance in terms ...
Read More
Westside Metro Extension Phase One | BRE Group

Birmingham Westside Metro – Centenary Square Extension

The Midland Metro Alliance (MMA) is working on behalf of Transport for West Midlands (TfWM), which is part of the ...
Read More
Musaimeer Pump Station and Outfall Qatar | BRE Group

Musaimeer Pumping Station and Outfall Tunnel

Musaimeer Pump Station and Outfall (MPSO) is one of the unique infrastructure projects of Ashghal which aims to provide a ...
Read More
Bybanen D12 Store Lungegårdsvann | BRE Group

Bybanen D12 Fløen – Kronstad

The Bybanen tram-project is part of the Miljøløftet, a common term for the urban growth agreement and the city infrastructure ...
Read More
DCIM100MEDIADJI 0115JPG | BRE Group

A6 Randalstown to Castledawson Dualling

Delivered by the Department for Infrastructure the A6 Dualling Scheme upgrades 14.7 kilometres of Transport Corridor between Randalstown and Castledawson, ...
Read More

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags