Bygrave Anaerobic Digestion Plant | CEEQUAL

Bygrave Anaerobic Digestion Plant

Bygrave Anaerobic Digestion Plant BRE Group

CEEQUAL Excellent (75.5%) – Whole Project Award
Version 5, July 2014 | Baldock, Hertfordshire, England, UK

ClientBiogen
DesignerRolton Group
ConstructionToureen Group
Assessor: Graeme Outridge (Biogen)
Verifier: Catherine Arotsky (Rickaby Thompson Associates Ltd)

Project Summary

The £12m anaerobic digestion (AD) plant at Bygrave Lodge Farm, near Baldock in Hertfordshire was developed as part of Biogen’s strategy to build a network of green energy plants across the UK. The AD plant will provide a sustainable food waste treatment solution for homes and businesses in Hertfordshire and the surrounding areas.

Due for completion in November 2014, the facility will process 45,000 tonnes per year of food waste from retailers, manufacturers and households to produce 2.2 MW of renewable electricity for up to 3,600 homes and a nutrient rich biofertiliser for nearby farmland.
Bygrave Lodge is Biogen’s first AD plant to undergo CEEQUAL assessment and a first also for construction partners Toureen Group and designers for the project, Rolton Group.

More significantly for the industry, this is the first ever sustainability in civil engineering award for a food waste AD plant in the UK.

Bygrave Anaerobic Digestion Plant | CEEQUAL
Exterior of Bygrave Anaerobic Digestion Plant

Challenges and Achievements

The anaerobic digestion of waste is in itself a very sustainable process, but constructing such a plant in a greenbelt area presents many challenges, not least limiting the impact on the local environment.

Protecting and preserving the natural landscape was given priority consideration during the planning and construction phases of the project. In addition opportunities were sought to enrich the landscape and enhance the area wherever possible.

Planning regulations recommended the planting of several different species of trees [see appendix] to screen the AD plant, but the quantity was not specified. Long before the site was completed 14,000 trees were planted, forming a screen and also enhancing the future landscape. The tree species chosen and planted will be good food and habitat providers for birdlife once mature.

Other activities undertaken to improve the ecology and diversity:

  • A screening bund was created using surplus materials from the construction site thus ensuring zero waste sent to landfill.
  • A balancing pond [flood basin] developed on site was adapted in order to provide pond habitat for amphibians and other wildlife.
  • Bunds were adapted to form beetle banks which will create a suitable habitat for invertebrates.
  • Perching posts for corn buntings, a species which has been in decline, have been installed to encourage their return to the area.
  • LED lighting was installed internally and externally providing low power consumption, low maintenance and less light pollution overall.
  • Rainwater harvesting was implemented to reduce potable water usage . All water on paved areas is captured and sent to the balancing pond also for re-use on site.
Bygrave Anaerobic Digestion Plant | CEEQUAL
Large Balancing Pond Planting Underway Panorama 9th October 2013

How did CEEQUAL influence your project?

The majority of the Bygrave site was initially considered to be of relatively low ecological value but as a result of the actions undertaken during planning and construction, Biogen, in keeping with its values, has succeeded in not only protecting the environment but also improving and enhancing it thus assisting ecological diversity of the local area.

The CEEQUAL assessment recognises and rewards best practice which is invaluable to a relatively new industry such as anaerobic digestion. Undertaking the assessment has helped Biogen develop a greater awareness of approaches to sustainability and provided standards and guidelines which can be implemented in future projects. The assessment has helped shape the decision making process when considering the whole lifecycle of the Bygrave project and it is expected this will bring environmental benefits and cost savings to future developments.

Appendix

Bygrave Anaerobic Digestion Plant | CEEQUAL

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

Dundee Central Waterfront 02 full BRE Group

Dundee Central Waterfront: Contract 4

The transformation of Dundee’s waterfront reached a major milestone at the end of February 2016 with the opening to the ...
Read More
Crossrail Surface Works Stockley Flyover 01 FINAL BRE Group
| CEEQUAL Case Studies, Rail, UK

Crossrail Surface Works: Stockley Flyover

Stockley Flyover is a £90 million Crossrail Project and after number of years of construction is almost complete. The objective ...
Read More
Crossrail Whitechapel And Liverpool Steet SCL 08 BRE Group
| CEEQUAL Case Studies, Rail, UK

Crossrail: Eleanor Street & Mile End Road Shafts

Crossrail is delivering the Elizabeth line – a new railway for London and the South East. When it opens through ...
Read More
Colwyn Bay Waterfront Project LS 1 E1576834169108 BRE Group

Colwyn Bay Waterfront Project – Design of Vibrant and Viable Places (VVP) Phase 2 Promenade Enhancements

This project represents Phase 2 of the Colwyn Bay Waterfront Project, a major scheme delivered by Conwy County Borough Council ...
Read More
Crossrail Whitechapel And Liverpool Steet SCL 01A BRE Group
| CEEQUAL Case Studies, Rail, UK

Crossrail: Whitechapel and Liverpool Street SCL

Crossrail C510 Whitechapel and Liverpool Street Station Tunnels is a major tunnelling contract awarded as part of Crossrail, Europe’s largest ...
Read More
Peace Bridge 4 BRE Group

The Peace Bridge

The Peace Bridge is a 312 metre self-anchored suspension bridge for the use of pedestrians and cyclists and the newest ...
Read More

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags