Bygrave Anaerobic Digestion Plant | CEEQUAL

Bygrave Anaerobic Digestion Plant

Bygrave Anaerobic Digestion Plant BRE Group

CEEQUAL Excellent (75.5%) – Whole Project Award
Version 5, July 2014 | Baldock, Hertfordshire, England, UK

ClientBiogen
DesignerRolton Group
ConstructionToureen Group
Assessor: Graeme Outridge (Biogen)
Verifier: Catherine Arotsky (Rickaby Thompson Associates Ltd)

Project Summary

The £12m anaerobic digestion (AD) plant at Bygrave Lodge Farm, near Baldock in Hertfordshire was developed as part of Biogen’s strategy to build a network of green energy plants across the UK. The AD plant will provide a sustainable food waste treatment solution for homes and businesses in Hertfordshire and the surrounding areas.

Due for completion in November 2014, the facility will process 45,000 tonnes per year of food waste from retailers, manufacturers and households to produce 2.2 MW of renewable electricity for up to 3,600 homes and a nutrient rich biofertiliser for nearby farmland.
Bygrave Lodge is Biogen’s first AD plant to undergo CEEQUAL assessment and a first also for construction partners Toureen Group and designers for the project, Rolton Group.

More significantly for the industry, this is the first ever sustainability in civil engineering award for a food waste AD plant in the UK.

Bygrave Anaerobic Digestion Plant | CEEQUAL
Exterior of Bygrave Anaerobic Digestion Plant

Challenges and Achievements

The anaerobic digestion of waste is in itself a very sustainable process, but constructing such a plant in a greenbelt area presents many challenges, not least limiting the impact on the local environment.

Protecting and preserving the natural landscape was given priority consideration during the planning and construction phases of the project. In addition opportunities were sought to enrich the landscape and enhance the area wherever possible.

Planning regulations recommended the planting of several different species of trees [see appendix] to screen the AD plant, but the quantity was not specified. Long before the site was completed 14,000 trees were planted, forming a screen and also enhancing the future landscape. The tree species chosen and planted will be good food and habitat providers for birdlife once mature.

Other activities undertaken to improve the ecology and diversity:

  • A screening bund was created using surplus materials from the construction site thus ensuring zero waste sent to landfill.
  • A balancing pond [flood basin] developed on site was adapted in order to provide pond habitat for amphibians and other wildlife.
  • Bunds were adapted to form beetle banks which will create a suitable habitat for invertebrates.
  • Perching posts for corn buntings, a species which has been in decline, have been installed to encourage their return to the area.
  • LED lighting was installed internally and externally providing low power consumption, low maintenance and less light pollution overall.
  • Rainwater harvesting was implemented to reduce potable water usage . All water on paved areas is captured and sent to the balancing pond also for re-use on site.
Bygrave Anaerobic Digestion Plant | CEEQUAL
Large Balancing Pond Planting Underway Panorama 9th October 2013

How did CEEQUAL influence your project?

The majority of the Bygrave site was initially considered to be of relatively low ecological value but as a result of the actions undertaken during planning and construction, Biogen, in keeping with its values, has succeeded in not only protecting the environment but also improving and enhancing it thus assisting ecological diversity of the local area.

The CEEQUAL assessment recognises and rewards best practice which is invaluable to a relatively new industry such as anaerobic digestion. Undertaking the assessment has helped Biogen develop a greater awareness of approaches to sustainability and provided standards and guidelines which can be implemented in future projects. The assessment has helped shape the decision making process when considering the whole lifecycle of the Bygrave project and it is expected this will bring environmental benefits and cost savings to future developments.

Appendix

Bygrave Anaerobic Digestion Plant | CEEQUAL

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

Top View Of A Young Green Forest In Spring Or Summer BRE Group

Foryd Harbour Public Realm

The Rhyl Harbour project formed part of a stream that included a sustainable transport bridge, coastal erosion and flood protection ...
Read More
Crossrail Connaught Tunnel 01A Featured Image 16 9 BRE Group
| CEEQUAL Case Studies, Rail, UK

Crossrail: Connaught Tunnel and Surface Railway

The Connaught Tunnel Refurbishment Project transformed an abandoned 1878 Victorian tunnel and disused railway and re-engineered it to receive the ...
Read More
Colwyn Bay Phase 1 Flood Defence Featured Image 01 BRE Group

Colwyn Bay: Phase 1 – Flood Defence

The coastal defences along the Colwyn Bay frontage had several key issues to address through developments and improvements. As a ...
Read More
Bulford Road Featured Image Alun Griffiths Contractors Ltd BRE Group

Bulford Road Improvement Scheme

The Bulford Road Improvement project was conceived and designed to provide significant improvements to a single lane road between the ...
Read More
Looking Directly Up At The Skyline Of The Financial District In Central London Stock Image BRE Group

Baltic Triangle Public Realm Improvements

The Baltic Triangle scheme was formulated to implement improvements to the public realm in the creative industries location of the ...
Read More
Balloo 4 BRE Group

Balloo Waste Transfer Station and Recycling Centre, Bangor

The Waste Transfer Station is a facility comprising 10,000m2 of machine, technology and administrative support space, which will swallow the ...
Read More

Get in touch

Contact us now or call us on +443330147880 if you would like to talk to our team about how CEEQUAL can support you.

Tags