Beragh Flood Alleviation Scheme | CEEQUAL

Beragh Flood Alleviation Scheme

Beragh FAS 01 Featured Image BRE Group

CEEQUAL Excellent (86.0%) – Whole Team Award
Version 5, April 2016 | Beragh, County Tyrone, UK (Northern Ireland)

Sustainability strategy: Excellent (94.2%)

ClientRivers Agency
DesignerRivers Agency
Contractor: BSG Civil Engineering Ltd.
Assessor: Wayne Moore (Rivers Agency NI)

Project Summary

In June 2014, Rivers Agency commenced construction of the £1.4 million flood alleviation scheme on the Cloughfin River in Beragh. The scheme provides flood protection to 17 residential properties and the Red Knights GAA Club facilities, both of which were affected by flooding in 2008 and 2011.

The scheme was submitted for a CEEQUAL Whole Project Award to encourage improved environmental and social performance in project specification, design, and construction.

The flood protection elements of the project, which included flood walls and placement of a culvert section, were combined with environmental enhancement measures, such as tree planting on the riverbanks and the introduction of in channel features including rock ‘diamonds’ and boulders.

The project team, comprising the client and designer (Rivers Agency) and contractor (BSG Civil Engineering) engaged with the community throughout the scheme to minimise disruption.  They also took the opportunity to inform and educate local primary school children on the history of flooding in Beragh and the work carried out to resolve the issues.

The scheme was completed in July 2015 and was awarded an Excellent Sustainability Strategy Assessment Award (Section 1 only) with a score of 94.2% and an Excellent Sustainability Performance Assessment Whole Team Award (Sections 2-9) with a score of 86.0%.

Award Presentation

Beragh Flood Alleviation Scheme | CEEQUAL
Left to Right: Owen McGivern – Rivers Agency Head of Operations, Ian Nicholson – CEEQUAL Technical Director, Sam Managh – BSG Civil Engineering Site Engineer.

CEEQUAL insights and case studies

Browse the latest insights, thinking and case studies from CEEQUAL

 

Shinfield Eastern Aerial BRE Group

Shinfield Eastern Relief Road

Construction of a new single span overbridge over the M4 with approximately 1.6 km of relief road around the village ...
Read More
Filton Bank After BRE Group
| CEEQUAL Case Studies, Rail, UK

Dr Days to Filton Abbey Wood Capacity Improvement (also referred to as “Filton Bank 4 Track”)

Filton Bank was a design and build project, reinstating 2 former tracks between Dr Days Junction to the South and ...
Read More
Barkarbystaden West Ticket Hall Entrance BRE Group
| CEEQUAL Case Studies, Rail, Scandinavia

Blue line to Barkarby, FUT4, Extended Metro Administration, Region Stockholm

The clients aim was to be able to measure the sustainability level between the different metro extension projects, make them ...
Read More
Dover 1 BRE Group

Dover Western Docks Revival (DWDR) – Port of Dover

Dover Western Docks Revival (DWDR) is a one-off opportunity for the regeneration of Dover, bringing new investment into the area ...
Read More
M4 Junction 28 BRE Group

M4 Junction 28 Improvements

The improvement of the junction is seen by the Welsh Government as an important part of its programme for economic ...
Read More
Barkarby BRE Group

Blue line to Barkarby Access tunnel Robothöjden-Landningsbanan

The project achieved a CEEQUAL Excellent rating. CEEQUAL enabled more discussions in the project group about sustainability which lead to ...